Hello! Any ballast experts there?

Reply
 
Thread Tools
  #1  
Old 12th April 2010, 12:43
Jonathan Jonathan is offline  
Member
 
Join Date: Apr 2010
Location: Moscow
Posts: 4
Hello! Any ballast experts there?

Hello to all the members of Railway Forum! I want to open my membership with a question that I haven't been able to find the answer to anywhere on the web...what would be a fairly representative range of volumes in m3 for the amount of gravel/ballast used in the construction of a two-tracked railway line (I am particularly interested in what this figure might be in the Russian Railway system). I'm sure that among all the members there will be somebody who will answer my plea! Many thanks, and thanks for having me on board.


Reply With Quote
  #2  
Old 12th April 2010, 13:47
pavorossi pavorossi is offline  
Senior Member
 
Join Date: Nov 2005
Location: Lancashire
Posts: 1,651
Images: 69
Hello and welcome to the forum Jonathan. I'm afraid I don't know the answer to your question, but I'm sure one of members will be able to help.
__________________
Adam
East Lancs TTI
Reply With Quote
  #3  
Old 12th April 2010, 13:51
locojoe's Avatar
locojoe locojoe is offline  
Registered Member
 
Join Date: Oct 2006
Location: London England
Posts: 951
Images: 47
Hello

Quote:
Originally Posted by Jonathan View Post
Hello to all the members of Railway Forum! I want to open my membership with a question that I haven't been able to find the answer to anywhere on the web...what would be a fairly representative range of volumes in m3 for the amount of gravel/ballast used in the construction of a two-tracked railway line (I am particularly interested in what this figure might be in the Russian Railway system). I'm sure that among all the members there will be somebody who will answer my plea! Many thanks, and thanks for having me on board.

Hello Jonathan Welcome to the railway forum. Sorry I can't help with your question about gravel/ballast.
__________________
locojoe
When I read about the evils of drink I gave up reading
Reply With Quote
  #4  
Old 12th April 2010, 13:52
ccmmick's Avatar
ccmmick ccmmick is offline  
Senior Member
 
Join Date: Aug 2009
Location: St Austell
Posts: 1,109
Images: 71
Hi Jonathan and welcome.
Not me either the only thing i remember is the speed to go to lay the ballast

Sorry
ccmmick.
__________________
Sometimes i think to myself
I dont know and other times
I dont know what to think

Reply With Quote
  #5  
Old 12th April 2010, 14:11
Jonathan Jonathan is offline  
Member
 
Join Date: Apr 2010
Location: Moscow
Posts: 4
Thanks, I'll keep my fingers crossed!
Reply With Quote
  #6  
Old 12th April 2010, 18:02
Ploughman Ploughman is offline  
Senior Member
 
Join Date: Dec 2009
Location: York
Posts: 333
For a single line of railway you are looking at just about 1 cu M per metre of ballast.
approx 3.7m x 0.25m depth plus top ballast to fill sleeper bays.
If a greater depth is required then figuress change.
__________________
Bryan

http://www.yorkareagroup.co.uk/
Reply With Quote
  #7  
Old 12th April 2010, 19:56
DSY011's Avatar
DSY011 DSY011 is offline  
Station Manager
 
Join Date: Nov 2005
Location: BRISTOL U.K.
Posts: 4,464
Images: 547
Hello Jonathan and welcome to the Railway forum. There is always someone on this forum that has the answer to almost any railway related question, if not, they know where to get the information for you.
__________________
The Old Git, Syd
Reply With Quote
  #8  
Old 12th April 2010, 20:35
John H-T's Avatar
John H-T John H-T is offline
Station Manager
 
Join Date: Nov 2005
Location: Derbyshire
Posts: 6,351
Images: 528
Hello Jonathan and welcome to the Forum. I cannot give you exact figures but I can say that 100 tons of ballast doesn't go very far! We are relaying a lot of track at the moment and I will ask the man who orders the ballast how he works out quantities.

Best wishes,

John H-T.
__________________
Ecclesbourne Valley Railway.
LMS Patriot Group.
LMS Carriage Association.
Belper Model Railway Group.
Reply With Quote
  #9  
Old 12th April 2010, 20:43
Mendipman319's Avatar
Mendipman319 Mendipman319 is offline  
Senior Member
 
Join Date: Apr 2010
Location: Glastonbury, UK
Posts: 125
Images: 33
welcome to the forum! sorry i cant answer your question as John T-T said i should know but i cant remember
Reply With Quote
  #10  
Old 13th April 2010, 09:41
Jonathan Jonathan is offline  
Member
 
Join Date: Apr 2010
Location: Moscow
Posts: 4
Ploughman, many thanks for your response, I really appreciate it! I am currently working on developing a quarry producing among other things railway ballast up in the Russian arctic circle, and this kind of information is surprisingly hard to come by.

John H-T, I look forward to hearing how the man who orders your ballast works out quantities; it will be particularly interesting to have a "live" example.
Reply With Quote
Reply


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is Off
HTML code is Off

Forum Jump


All times are GMT +1. The time now is 07:36.


Powered by vBulletin® Version 3.8.4
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.